Project Planning

Structuring a project so it can be delivered, costed and reported against — scope, breakdown, schedule and gates.

Workflow

  1. 01Initiation
  2. 02Work Breakdown
  3. 03Scheduling
  4. 04Baseline
  5. 05Gate Approval
  6. 06Progress Measurement

If you change this

It implies 3 topics across one module.

See the path ahead →

Why it matters

A schedule is the visible output. The work breakdown structure is the consequential one: it determines what cost can be attributed to, what can be reported, and whether the project's financial position can be produced at all.

  • It is the reporting spine: Cost, commitment and progress all attach to the breakdown. A structure that suits delivery but not finance produces a mapping layer, and the mapping layer becomes a spreadsheet.
  • Gates only work against a baseline: Without one that changes formally, variance reporting is a comparison against the current opinion.
  • Progress has to be measurable: Percent complete that is self-reported effort will sit at ninety for months.

The workflow

  1. 01

    Initiation

    Scope, objectives and success measures defined, with the funding source and approval path named.

  2. 02

    Work breakdown

    Decomposed to the level work is assigned and cost is captured — and to the level external reporting needs.

  3. 03

    Scheduling

    Sequenced with real dependencies, resource-loaded against actual availability.

  4. 04

    Baseline

    Scope, schedule and budget frozen, with a change route for anything after.

  5. 05

    Gate approval

    Approved to proceed against criteria set in advance.

  6. 06

    Progress measurement

    Physical progress measured against the baseline, not estimated against the remaining effort.

Design the breakdown against both audiences at once. Delivery wants it by project and phase; finance and the funder want it by asset class, service or category. One structure has to carry both, and retrofitting the second is where the manual reporting comes from.

What you need in place

  • A breakdown that serves finance and delivery: Agreed jointly, tested against the actual external reporting categories.
  • A baseline that only changes formally: Otherwise there is nothing to measure against.
  • Gate criteria set in advance: With a real option to not proceed.
  • Physical progress measures: Milestones or quantities, not effort consumed.
  • Alignment to the chart of accounts: The project structure has to fit the ledger it posts into.
  • Dependency mapping across projects: Portfolio-level constraints are invisible inside a single plan.

Questions to ask

01Two audiences

Does the breakdown produce the external report natively?

If it needs a mapping layer, that layer is where the effort will go.

02Baseline

What is the baseline, and when did it last formally change?

Informal drift makes variance meaningless.

03Progress

How is percent complete determined?

Self-reported effort is why projects are ninety percent complete for a quarter.

04Gates

Has a gate ever stopped a project here?

If not, the gate is a reporting event.

05Ledger fit

Does the structure fit the chart of accounts?

Establish this before design, not during build.

06Resources

Is the schedule loaded against real availability?

A plan resourced on notional capacity is a forecast of slippage.

Metrics and KPIs to track

Schedule performance

Milestones met on the baseline date, and cumulative slip.

Baseline changes

Formal changes per period, with cause.

Progress measurement basis

Share of projects measured on physical progress.

Gate outcomes

Proceed, conditional and deferred, as a distribution.

Planning accuracy

Estimate at initiation against final outcome, trended.

Alongside this

All of Projects and Portfolio (PPM)