Project management plan

Alpha

How the programme will actually be run: decision rights, one plan, the change route, and what each gate has to prove.

What it is for

To make the programme legible — what is being spent, what is being decided, what is slipping, and who is accountable — before any of those become contested.

Audience
Steering committee, workstream leads, assurance.
The decision it supports
Whether this programme can be governed at the speed it needs.

Inputs — 7 blocking

Blocking means the document cannot be honestly drafted without it. The rest can be left open and marked as such.

Scope baseline and exclusions

From /scope

The areas in scope, the streams they sit on, the modules dragged in, and what is explicitly out.

Delivery

Governance structure and decision rights

In the library

Forums defined by what they decide, not by seniority, with terms of reference, quorum and cadence.

Delivery · Programme Governance

Delegation mapping

Only you have it

Financial and scope authority traced back to the organisation's own delegation instrument, so approvals inside the programme are valid.

Finance · Programme Governance

One integrated plan

From /scope

A single schedule across workstreams with dependencies named. Not one plan per workstream stapled together.

Delivery · PMO & Programme Governance

Gate criteria

In the library

What each gate has to prove, agreed while nobody is under pressure to say yes.

Delivery and assurance · PMO & Programme Governance

Resourcing and backfill

Only you have it

Named people at named percentages, with backfill funded and confirmed by the managers losing them.

Business owners · Digital Transformation Readiness Checklist

Change control route

In the library

How scope, budget and schedule change deliberately: who raises, who assesses impact, who approves at which threshold, and how cumulative impact is reported.

Delivery · Change Requests

Draft around these if needed

Risk, issue, decision and action registers

In the library

One of each, across the programme, with single named owners and visible ageing.

Delivery · Actions and Decisions

Reporting cadence and audience

Only you have it

What each forum gets, and what it is expected to do with it. Papers ahead of the meeting, with a recommendation.

Delivery · Programme Governance

Assurance arrangement

In the library

Who checks the programme independently, and who they report to. Assurance reporting into the programme director is not assurance.

Sponsor · Be a Hero

Decision latency baseline

Only you have it

How long a decision takes today, measured before mobilisation. A programme needs them faster, not slower.

Delivery · Empower People

What your scope already answers

  • Scope and exclusions: 6 topics across 3 modules — including Customer Relationship Management, Supply Chain Management, unpicked.
  • Interfaces to specify: 4, including the hand-offs where only one side is being changed.
  • Release order: 1. Order Management · 2. Accounts Receivable
  • Assumed already in place: Inventory, General Ledger — depended on, not included.

First draft

2/9 sections the scope could speak to

Generated from your scope. It is not a finished document and it does not pretend to be — where a section needs something only you have, it says so rather than inventing a plausible sentence, because plausible sentences are the ones that get left in.

Project management plan

Scope, exclusions and baseline

The change covers 1 chosen area — Order to Cash — which in turn implies 6 topics across 3 modules: Customer Relationship Management, Supply Chain Management and Financial Accounting.

Customer Relationship Management and Supply Chain Management were not chosen. They are in scope because the value streams the chosen areas sit on cross into them, so work happens there whether or not it was planned for. This needs to be accepted or the scope reduced — it should not be left unstated.

The scope depends on Inventory and General Ledger without including them. That is fine if they are staying as they are, and a gap in the plan otherwise.

Governance, decision rights and delegations

To write. The scope cannot supply this one.

The integrated plan and critical path

The dependency order gives 2 releases: 1. Order Management; 2. Accounts Receivable. Items within a release have no unmet prerequisite inside the scope and can start together.

Gates and what each one proves

To write. The scope cannot supply this one.

Resourcing, backfill and capacity

To write. The scope cannot supply this one.

Change control and the baseline discipline

To write. The scope cannot supply this one.

Risk, issue and decision management

To write. The scope cannot supply this one.

Reporting, assurance and escalation

To write. The scope cannot supply this one.

Closure: what has to be true for this to end

To write. The scope cannot supply this one.

Still needed

  • Delegation mappingFinancial and scope authority traced back to the organisation's own delegation instrument, so approvals inside the programme are valid.
  • Resourcing and backfillNamed people at named percentages, with backfill funded and confirmed by the managers losing them.
As markdown, to lift into a document
# Project management plan

## Scope, exclusions and baseline

The change covers 1 chosen area — Order to Cash — which in turn implies 6 topics across 3 modules: Customer Relationship Management, Supply Chain Management and Financial Accounting.

Customer Relationship Management and Supply Chain Management were not chosen. They are in scope because the value streams the chosen areas sit on cross into them, so work happens there whether or not it was planned for. This needs to be accepted or the scope reduced — it should not be left unstated.

The scope depends on Inventory and General Ledger without including them. That is fine if they are staying as they are, and a gap in the plan otherwise.

## Governance, decision rights and delegations

> To write. The scope cannot supply this one.

## The integrated plan and critical path

The dependency order gives 2 releases: 1. Order Management; 2. Accounts Receivable. Items within a release have no unmet prerequisite inside the scope and can start together.

## Gates and what each one proves

> To write. The scope cannot supply this one.

## Resourcing, backfill and capacity

> To write. The scope cannot supply this one.

## Change control and the baseline discipline

> To write. The scope cannot supply this one.

## Risk, issue and decision management

> To write. The scope cannot supply this one.

## Reporting, assurance and escalation

> To write. The scope cannot supply this one.

## Closure: what has to be true for this to end

> To write. The scope cannot supply this one.

## Still needed

- **Delegation mapping** — Financial and scope authority traced back to the organisation's own delegation instrument, so approvals inside the programme are valid.
- **Resourcing and backfill** — Named people at named percentages, with backfill funded and confirmed by the managers losing them.

_First draft from a scope. 2 of 9 sections had something the scope could say; the rest need a person, and so does everything under Still needed._

Outline

  1. 01Scope, exclusions and baseline
  2. 02Governance, decision rights and delegations
  3. 03The integrated plan and critical path
  4. 04Gates and what each one proves
  5. 05Resourcing, backfill and capacity
  6. 06Change control and the baseline discipline
  7. 07Risk, issue and decision management
  8. 08Reporting, assurance and escalation
  9. 09Closure: what has to be true for this to end

What separates a useful one from a compliant one

  • Every forum has stated decision rights, including what it cannot decide.
  • There is one schedule, not one per workstream.
  • Gate criteria were set before anyone was under date pressure.
  • Escalation has a service level, so raised issues cannot simply sit.
  • The plan says what would make the programme stop.

The rest of the set